Flemington, NJ

Manufacturing · Engineering · Capital Project Advisory

From 50 million pounds
to 180 million.

Annual capacity delivered under one capital program · 2013–2026

Thirty years leading capital projects, facility expansions, and manufacturing engineering for companies that cannot afford a missed startup.

Request a consultation Estimate a project Order-of-magnitude cost and schedule in about two minutes.
Fig. 1 — Capital project execution, plan through startup Line status — 50M lbs/yr
01Planning & Budgeting
02Design & Engineering
03Procurement
04Construction
05Installation
06Commissioning
Position

Most capital projects fail on paper, long before anyone breaks ground.

Budgets built on optimism. Schedules that assume nothing slips. Scope agreed verbally and discovered in the field. KJW Consulting is engaged by owners, executive teams, and private-equity firms to put an experienced operator on the project before those decisions harden — and to stay on it through commissioning and startup, when the plan meets the plant floor.

Kevin J. Walsh, PMP, spent thirty years inside manufacturing organizations rather than advising them from outside — as Vice President of Engineering, Director of Engineering, and project manager across multi-site networks in the United States and Mexico. The advice is operator-side, and it is accountable to a startup date.

Record
$30M
Annual capital investment portfolios directed
75+
Major capital projects managed across three decades
180M lbs
Annual production capacity delivered, up from 50M
$7M
Annual savings generated through network optimization
6
Acquisitions carried through engineering due diligence and integration
~40%
Labor requirement reduction identified in a three-year capital roadmap
How a project runs

Six phases. The expensive mistakes are made in the first two.

Engagement can begin at any phase, but the leverage is front-loaded: scope and budget decisions made in planning set the ceiling on everything that follows.

Planning & Budgeting

Scope, order-of-magnitude cost, and a schedule that survives contact with reality. A capital request built on wishful numbers is approved once and paid for repeatedly — this is the cheapest phase in which to be wrong, and the only one where being right is free.

  • Scope definition and basis of estimate
  • Capital request package and approval support
  • Schedule with identified long-lead constraints
  • Risk register with named accountability
Specialties

Seven areas of practice.

Capital Project Management
Leadership and oversight for major capital projects, from early planning and budgeting through construction, equipment installation, commissioning, and startup.
Facility Relocations & Expansions
Planning and coordination for manufacturing relocations, consolidations, expansions, and new-facility development, with an emphasis on minimizing operational disruption.
Manufacturing Engineering
Evaluation and improvement of production systems, equipment layouts, automation, utilities, material flow, and facility infrastructure.
Operational Integration
Support for mergers, acquisitions, and facility integrations — equipment transfers, capacity planning, process alignment, and consolidation strategy.
Project Planning & Risk Management
Realistic budgets, schedules, scopes, and execution plans that surface risk early and establish clear accountability before it is needed.
Contractor & Vendor Management
Selection, coordination, and oversight of architects, engineers, contractors, equipment manufacturers, and other project partners.
Executive Advisory Services
Objective guidance for business owners, private-equity firms, and executive teams evaluating capital investments, facility strategies, and operational opportunities.
Selected work

Three programs, described by what they moved.

Client names and project photography are withheld under confidentiality and non-compete obligations. Detailed references are available under NDA on request.

Principal

Kevin J. Walsh, PMP

Manufacturing and engineering executive with more than thirty years of leadership across complex manufacturing environments — capital investment programs, multi-site engineering organizations, transformational capacity expansions, and new facility construction. KJW Consulting is his practice.

Project Management Professional (PMP)
Project Management Institute
Master's Certification, Project Management
Univ. of Wisconsin School of Business
B.S. Business
DePaul University
Vice President of Engineering
2013 – 2026
Director of Engineering
2007 – 2012
Senior Engineering Manager
2002 – 2007
Estimator

Order-of-magnitude cost & schedule · AACE Class 5

What the project is likely to cost, before anyone draws it.

A concept-screening estimate built the way a capital committee expects to see one — equipment-factored, banded, and honest about its own accuracy. Two minutes here will tell you whether a project is worth the cost of a real study.

Inputs
Project type
Major equipment budget $3M
$250K$25M

Purchased cost of process equipment only — no installation, no building. If you have vendor quotes, use their total. If not, estimate from comparable equipment you have bought before.

Process character
Site condition
Conditions that apply
AACE Class 5 · Concept screening
$8.2M $17.6M
Total installed cost · Point estimate $11.8M
−30% low+50% high
Where the money goes
Schedule · 22 months to startup

Recommended contingency: 30% carried against the point estimate at this stage, released as definition matures. A Class 5 estimate that carries no contingency is not an estimate, it is a wish.

What this is. An equipment-factored estimate using published Lang factors, banded to AACE International's Class 5 accuracy range. It is built for one decision only: whether to fund a real study.

What it is not. Not a budget, not a quote, and not a basis for a capital request. Those need a Class 3 estimate built on actual drawings, quotes and a defined scope.

Send these numbers to Kevin
Method

The arithmetic is not a secret.

01 Equipment factoring Purchased equipment cost is multiplied by a Lang factor — 3.10 for solids handling, 3.63 for mixed processing, 4.74 for fluid processing — to reach total installed cost including materials, labour, engineering and indirects.
02 Site and scope modifiers Applied on top of the factored cost for site condition and for the conditions that reliably move real projects: sanitation standards, execution around live production, automation content, and utility capacity.
03 Class 5 banding The result is presented at −30% / +50%, inside AACE International's published Class 5 range of −20% to −50% low and +30% to +100% high, for projects at 0–2% definition.

Every capital project estimate is wrong. The useful question is whether it is wrong in a direction and by a magnitude you planned for. That is what the band is for, and it is why the number above is a range and not a figure.

Contact

Start with the project you are least sure about.

An initial conversation is a scoping call, not a sales call — what the project is, what it is expected to cost, and whether the schedule is real. If an engagement makes sense after that, it will be obvious to both of us.

Based inFlemington, New Jersey
EngagementsUnited States & Mexico
ResponseWithin one business day